Inside a £4.3bn grid link

Prysmian supplies the subsea cable for Eastern Green Link 2. Hitachi Energy and BAM build the converter stations at each end.

Peterhead and Drax converter stations linked by a subsea cable
Project value£4.3bnConstruction update · 6 Nov 2026

National Grid × SSEN Transmission

The owners reported completion of the first converter-building steel frame at Peterhead. The planned electricity link runs 505 km to Drax in Yorkshire.

What this figure covers

The value covers the whole project. Each contractor has a separate scope and payment schedule.

Primary source · Owner's construction report ↗